Stage 2: Core
Outcome
Section titled “Outcome”The controls most systems depend on are required by approved policy, carried out by written procedures and measured by standards. Systems know which controls the organization provides for them to inherit.
Artifacts to produce
Section titled “Artifacts to produce”| Family | Artifacts beyond the family policy | Main controls |
|---|---|---|
| Access control | Account management procedure; access request form; access review record; remote access standard | AC-2, AC-17 |
| Awareness and training | Training plan; training record log | AT-2, AT-3, AT-4 |
| Audit and accountability | Audit logging standard (event list); log review procedure | AU-2, AU-6 |
| Configuration management | Configuration Management Plan; baseline configuration standard; change request form; component inventory | CM-9, CM-2, CM-6, CM-3, CM-8 |
| Contingency planning | Contingency Plan; business impact analysis; test plan and after-action report | CP-2, CP-4 |
| Identification and authentication | Identification and authentication standard | IA-2, IA-5 |
| Incident response | Incident Response Plan; incident handling playbook; incident report form; tabletop exercise kit | IR-8, IR-4, IR-6, IR-3 |
| Personnel security | Access agreement; onboarding, transfer and termination checklist | PS-6, PS-4, PS-5 |
| Risk assessment | Vulnerability management standard | RA-5 |
| System and communications protection | Encryption and key management standard; boundary protection standard | SC-8, SC-12, SC-13, SC-28, SC-7 |
| PII processing and transparency (if you handle PII) | Privacy notice; privacy impact assessment | PT-5, RA-8 |
Each family also gets a decision worksheet listing the values its policy needs.
Templates available now
Section titled “Templates available now”| Artifact | Type | Main controls | Status |
|---|---|---|---|
| Access Control Policy | Policy | AC-1 | Draft |
| Access Control Decision Worksheet | Decision worksheet | AC-1 | Draft |
| Awareness and Training Policy | Policy | AT-1 | Draft |
| Awareness and Training Decision Worksheet | Decision worksheet | AT-1 | Draft |
| Audit and Accountability Policy | Policy | AU-1 | Draft |
| Audit and Accountability Decision Worksheet | Decision worksheet | AU-1 | Draft |
| Configuration Management Policy | Policy | CM-1 | Draft |
| Configuration Management Decision Worksheet | Decision worksheet | CM-1 | Draft |
| Contingency Planning Policy | Policy | CP-1 | Draft |
| Contingency Planning Decision Worksheet | Decision worksheet | CP-1 | Draft |
| Identification and Authentication Policy | Policy | IA-1 | Draft |
| Identification and Authentication Decision Worksheet | Decision worksheet | IA-1 | Draft |
| Incident Response Policy | Policy | IR-1 | Draft |
| Incident Response Decision Worksheet | Decision worksheet | IR-1 | Draft |
| Personnel Security Policy | Policy | PS-1 | Draft |
| Personnel Security Decision Worksheet | Decision worksheet | PS-1 | Draft |
| Personally Identifiable Information Processing and Transparency Policy | Policy | PT-1 | Draft |
| Personally Identifiable Information Processing and Transparency Decision Worksheet | Decision worksheet | PT-1 | Draft |
| System and Communications Protection Policy | Policy | SC-1 | Draft |
| System and Communications Protection Decision Worksheet | Decision worksheet | SC-1 | Draft |
| Access Agreement | Form or register | PS-6, PS-4, PS-8, PL-4 | Draft |
| Access Request Form | Form or register | AC-2, AC-2(2), AC-5, AC-6, AC-6(2) | Draft |
| Access Review Record | Form or register | AC-2, AC-2(3), AC-5, AC-6(7) | Draft |
| Account Management Procedure | Procedure | AC-2, AC-2(1), AC-2(2), AC-2(3), AC-2(4), AC-2(13), AC-5, AC-6(7), PS-4 | Draft |
| Audit Logging Standard | Standard | AU-2, AU-3, AU-3(1), AU-3(3), AU-4, AU-5, AU-8, AU-9, AU-9(4), AU-11, AU-12, AU-5(1), AU-5(2), AU-9(2), AU-9(3), AU-10, AU-12(1), AU-12(3) | Draft |
| Baseline Configuration Standard | Standard | CM-6, CM-6(1), CM-6(2), CM-2, CM-2(2), CM-2(3), CM-2(7), CM-7, CM-7(1) | Draft |
| Boundary Protection Standard | Standard | SC-7, SC-7(3), SC-7(4), SC-7(5), SC-7(7), SC-7(8), SC-7(18), SC-7(21), AC-4 | Draft |
| Business Impact Analysis | Report | CP-2, CP-2(3), CP-2(8) | Draft |
| Change Request Form | Form or register | CM-3, CM-3(2), CM-4, CM-4(1), CM-4(2) | Draft |
| Component Inventory | Form or register | CM-8, CM-8(1), CM-8(2), CM-8(3), CM-8(4), PE-16, MP-7 | Draft |
| Configuration Management Plan | Plan | CM-9, CM-1, CM-2, CM-2(3), CM-3, CM-3(1), CM-3(4), CM-5 | Draft |
| Encryption and Key Management Standard | Standard | SC-8, SC-8(1), SC-12, SC-12(1), SC-13, SC-17, SC-28, SC-28(1) | Draft |
| Identification and Authentication Standard | Standard | IA-2, IA-2(1), IA-2(2), IA-2(8), IA-2(12), IA-5, IA-5(1), IA-5(2), IA-5(6), IA-3, IA-4, IA-4(4), IA-6, IA-7, IA-8, IA-8(1), IA-8(2), IA-8(4), IA-11, IA-12, AC-7 | Draft |
| Incident Handling Playbook | Procedure | IR-4, IR-4(1), IR-5, IR-6, IR-6(1), IR-6(3), IR-7, IR-8(1) | Draft |
| Incident Report Form | Form or register | IR-6, IR-6(1), IR-5, IR-7, IR-8(1) | Draft |
| Incident Response Plan | Plan | IR-8, IR-8(1), IR-4, IR-5, IR-6, IR-7, IR-2, IR-3 | Draft |
| Information System Contingency Plan | Plan | CP-2, CP-2(1), CP-2(3), CP-2(8), CP-6, CP-7, CP-8, CP-9, CP-10 | Draft |
| Log Review Procedure | Procedure | AU-6, AU-6(1), AU-6(3), AU-6(5), AU-6(6), AU-7, AU-7(1) | Draft |
| Onboarding, Transfer and Termination Checklist | Form or register | PS-4, PS-5, PS-3, PS-6, PS-7, AC-2, AT-2 | Draft |
| Privacy Impact Assessment | Report | RA-8, PT-2, PT-3, PT-4, PT-5, PT-7, PT-8, SC-7(24), RA-3 | Draft |
| Privacy Notice | Form or register | PT-5, PT-5(2), PM-20, PM-20(1), PT-2, PT-3, PT-4, PT-7 | Draft |
| Remote Access Standard | Standard | AC-17, AC-17(1), AC-17(2), AC-17(3), AC-17(4), AC-12, SC-10 | Draft |
| Security and Privacy Training Plan | Plan | AT-2, AT-2(2), AT-2(3), AT-3, AT-3(5), AT-4, PM-13, PM-14 | Draft |
| Tabletop Exercise Kit | Plan | IR-3, IR-3(2), IR-2(3), IR-4, IR-8 | Draft |
| Training Record Log | Form or register | AT-4, AT-2, AT-3 | Draft |
| Vulnerability Management Standard | Standard | RA-5, RA-5(2), RA-5(4), RA-5(5), RA-5(11) | Draft |
Decisions to make
Section titled “Decisions to make”- The values each family policy leaves open: review frequencies, time limits, approvers. The decision worksheets list them with typical values.
- Which controls the organization provides centrally (for example the identity provider, logging platform or training) and which each system provides itself.
- Where the organization sets a stricter value than a baseline requires.
| Role | Responsibility in this stage |
|---|---|
| Chief Information Security Officer | Owns the family policies and approves exceptions |
| Policy owners named in each policy | Write and maintain procedures and standards |
| Common control providers | Run the controls systems inherit and document them |
| System owners | Adopt the policies and record inheritance in their security plans |
RMF Prepare tasks this stage carries out
Section titled “RMF Prepare tasks this stage carries out”From SP 800-37 Rev. 2; see the Prepare step page. The mapping is the author’s judgment.
| Task | How this stage meets it |
|---|---|
| P-4 Tailored baselines and CSF profiles (optional) | Family policies set organization-wide values for baseline parameters |
| P-5 Common control identification | The list of centrally provided controls, recorded in the program plan and each security plan |
Done when
Section titled “Done when”Independent guidance, not an official NIST publication. Control text is from NIST SP 800-53 Rev. 5 and SP 800-53A (public domain). Original content is licensed CC BY 4.0; program templates and the downloadable kit are dedicated to the public domain under CC0 1.0.