Risk Management Strategy
Risk Management Strategy template: The organization-wide strategy for how the organization frames, assesses, responds to and monitors security and privacy risk, including its risk tolerance, following NIST SP 800-39 and RMF Prepare task P-2.
| Type | Program stage | Status | Template version | NIST basis |
|---|---|---|---|---|
| Plan | Foundation | Draft | 1.0.0 | SP 800-53 release 5.2.0 |
What it is
Section titled “What it is”The organization-wide strategy for how the organization frames, assesses, responds to and monitors security and privacy risk, including its risk tolerance, following NIST SP 800-39 and RMF Prepare task P-2.
Controls satisfied
Section titled “Controls satisfied”| Control | Title |
|---|---|
| PM-9 | Risk Management Strategy |
| PM-28 | Risk Framing |
| PM-29 | Risk Management Program Leadership Roles |
| PM-31 | Continuous Monitoring Strategy |
Downloads
Section titled “Downloads”| Variant | Ready to adopt | Annotated |
|---|---|---|
| All baselines | Word · Markdown | Word · Markdown |
Preview (annotated)
Section titled “Preview (annotated)”| Organization | Strategy version | Approved by | Approval date | Next review |
|---|---|---|---|---|
| Organization name | Fill in: version | Senior leader | Fill in: date | Fill in: date |
1. Purpose and scope
Section titled “1. Purpose and scope”This strategy sets out how Organization name manages security risk to its operations and assets, individuals, other organizations and the Nation from operating and using its systems (PM-9a.1), and privacy risk to individuals from its authorized processing of personally identifiable information (PM-9a.2). It applies across the organization, and every system’s risk decisions follow it (PM-9b).
Supply chain risk is managed under the supply chain risk management strategy (PM-30), which follows the risk tolerance set here.
2. Governance
Section titled “2. Governance”| Role | Part in risk management |
|---|---|
| Senior leader | Approves this strategy and sets risk tolerance (PM-28a.4) |
| Senior accountable official for risk management | Aligns security and privacy risk management with strategic, operational and budget planning (PM-29a) |
| Risk executive (function) | Reviews risk across the organization, resolves conflicts between units, and keeps decisions consistent (PM-29b). Members: Fill in: members. Meets Fill in: how often |
| Chief Information Security Officer | Maintains this strategy and runs the processes in it |
| Senior privacy official | Assesses and advises on privacy risk |
| Authorizing officials | Accept risk for their systems within the tolerance in section 3.3 |
| System owner | Assesses and responds to risk for the system, and proposes risk acceptance |
3. Risk framing
Section titled “3. Risk framing”3.1 Assumptions
Section titled “3.1 Assumptions”The assumptions that affect how Organization name assesses, responds to and monitors risk (PM-28a.1):
| Topic | Assumption |
|---|---|
| Threat sources | Fill in: who is likely to attack or disrupt the organization, for example criminal groups seeking ransom, insiders, suppliers, natural hazards |
| Vulnerabilities and conditions | Fill in: for example reliance on a few cloud providers, legacy systems that cannot be patched quickly |
| Consequences | Fill in: the harms that matter most, for example loss of service to customers, disclosure of personal data |
| Likelihood | Fill in: how likelihood is judged, for example from incident history, threat intelligence and sector reports |
3.2 Constraints
Section titled “3.2 Constraints”The constraints on risk assessment, response and monitoring (PM-28a.2): Fill in: for example budget limits, laws and contracts, legacy technology, staffing, supplier contracts.
3.3 Risk tolerance
Section titled “3.3 Risk tolerance”The Senior leader sets the organization’s risk tolerance as follows (PM-28a.4). For an authorized system, the authorizing official accepts risk at every level, after consulting the roles named for that level:
| Assessed risk level | Tolerance | Consult before accepting | Conditions |
|---|---|---|---|
| Very high | Fill in: for example not accepted; the system does not operate until the risk is reduced | Fill in: role, for example the risk executive (function) and the senior leader | Fill in: conditions |
| High | Fill in: for example accepted only for a limited time with a plan of action | Fill in: role, for example the risk executive (function) | Fill in: for example no longer than 90 days |
| Moderate | Fill in: tolerance | Fill in: role, for example the CISO | Fill in: conditions |
| Low | Fill in: tolerance | Fill in: role, for example none; reported in the risk register | Fill in: conditions |
| Very low | Fill in: tolerance | Fill in: role, for example none; reported in the risk register | Fill in: conditions |
Additional statements of tolerance: Fill in: for example no tolerance for loss of personal data of more than a set number of individuals; no single outage of a mission-essential service longer than a set time.
3.4 Priorities and trade-offs
Section titled “3.4 Priorities and trade-offs”The priorities and trade-offs Organization name considers in managing risk (PM-28a.3): Fill in: for example mission-essential services before internal services; availability of patient-facing systems weighed against speed of patching.
3.5 Distribution
Section titled “3.5 Distribution”The Chief Information Security Officer shall distribute the results of risk framing, this section, to Fill in: the personnel to receive the results of risk framing activities Typical: authorizing officials, system owners, information owners, the leaders of mission and business functions, the senior privacy official, and the senior accountable official for risk management. (PM-28b)
4. Risk assessment
Section titled “4. Risk assessment”| Item | Approach |
|---|---|
| Methodology | Fill in: for example NIST SP 800-30 Rev. 1, tailored as described here |
| Scale | Fill in: for example five qualitative levels, very low to very high, for likelihood, impact and risk |
| How likelihood and impact combine | Fill in: for example the risk matrix in an appendix |
| Threat information | Fill in: sources, for example the threat awareness program (PM-16), sector sharing groups, vendor advisories |
| Organization-level assessment | Fill in: how often the organization-wide risk assessment is done, and by whom |
| System-level assessments | Each system follows RA-3 and the risk assessment policy, using this methodology and scale |
| Privacy risk | Fill in: how privacy risk is assessed, for example through privacy impact assessments |
5. Risk response
Section titled “5. Risk response”5.1 Response options
Section titled “5.1 Response options”For each risk above the tolerance in section 3.3, the system owner proposes one of these responses: accept, avoid, mitigate, share or transfer. The proposal evaluates the alternatives for cost, effectiveness and effect on the mission.
5.2 Decisions
Section titled “5.2 Decisions”The authorizing official decides the response, after consulting the roles named in section 3.3 for the assessed risk level. Mitigations are tracked in the system’s plan of action and milestones (CA-5), within the organization’s plan of action and milestones process (PM-4).
5.3 Record of accepted risk
Section titled “5.3 Record of accepted risk”Each risk acceptance is recorded with the risk, its level, the reason, the compensating measures, the person who accepted it and an expiry date, in Fill in: where accepted risks are recorded, for example the risk register.
6. Risk monitoring
Section titled “6. Risk monitoring”Risk is monitored under the continuous monitoring strategy (PM-31), which sets the metrics, frequencies and reporting. These events trigger a new assessment of the affected risk: Fill in: for example a significant change to a system, a major incident, a new threat or vulnerability affecting the organization, a change in law or mission.
7. Approval
Section titled “7. Approval”| Name | Title | Signature | Date |
|---|---|---|---|
| Fill in: name | Senior leader | Fill in: date |
8. Review and change history
Section titled “8. Review and change history”- The Chief Information Security Officer shall review and update this strategy Fill in: the frequency at which to review and update the risk management strategy Typical: annually, and whenever organizational changes require it. (PM-9c)
- The Chief Information Security Officer shall review and update the risk framing in section 3 Fill in: the frequency for reviewing and updating risk framing considerations Typical: annually, with this strategy. (PM-28c)
| Version | Date | Change | Approved by |
|---|---|---|---|
| Fill in: version | Fill in: date | Fill in: summary of change | Fill in: name and title |
Federal systems
Section titled “Federal systems”OMB Circular A-130, Appendix I, section 3.a, requires agencies to implement “an agency-wide risk management process that frames, assesses, responds to, and monitors information security and privacy risk on an ongoing basis across the three organizational tiers.” Its footnote points to SP 800-39 and to section 5. Section 5.b, in the discussion of major provisions, says the risk management strategy “describes how an agency intends to assess risk, respond to risk, and monitor risk,” and that a credible strategy identifies risk assumptions, constraints, tolerance, and priorities and trade-offs.
- This strategy shall describe how the agency carries out the agency-wide risk management process that OMB Circular A-130, Appendix I, section 3.a, requires, and shall state the risk assumptions, constraints, tolerance, and priorities and trade-offs that section 5.b describes. (PM-9)
Independent guidance, not an official NIST publication. Control text is from NIST SP 800-53 Rev. 5 and SP 800-53A (public domain). Original content is licensed CC BY 4.0; program templates and the downloadable kit are dedicated to the public domain under CC0 1.0.